L.E.B.S. Electric Powers Major AdventHealth Sebring Expansion and the Future of Patient Care

Our L.E.B.S. Electric team recently completed extensive work on the AdventHealth Sebring Tower Expansion (AHSTE), a major project designed to strengthen the hospital today and prepare it for continued growth.

The expansion includes a three-story addition to the existing bed tower, with one floor fully built out and two additional floors planned for the future. Our work also included a major addition to the existing Central Energy Plant, two new 2-megawatt generators, and a new utility service.

A permanent power system was necessary for a mobile MRI unit, new generators were integrated to replace the existing generator systems and capture the old Emergency Distribution Plant into a new design, and we installed a new fire alarm system throughout the entire building.

Projects of this size and complexity take tremendous planning, coordination and craftsmanship. We’re proud to work with AdventHealth, Brassfield & Gorrie, and TLC Engineers to expand patient care in Sebring. 

But wait, there’s more. Stay tuned for the next phases that will add more than 100,000 square feet of new clinical space, advancing the technology used to diagnose and treat heart disease and expand the hospital’s capacity, transforming Sebring Hospital from 171 to 275 inpatient beds.

Big Milestone in Our Work at AdventHealth East Orlando Hospital

A big milestone for our work at AdventHealth East Orlando where we recently passed our AHCA inspection and all three 2MW generators are now allowed to be fully operational. A lot of hard work went into getting to this point, and we’re proud of the team that made it happen.

Next up, we’ll be swapping out the main switch for the utility feeders. During that time, the hospital will be running on the generators we just installed and patient care will not be interrupted. 

After that, we’ll wrap things up with a full facility simulated power loss test during off-peak hours to make sure the load shedding system functions properly. 

Keeping critical facilities powered and ready when it counts is the kind of work that matters. We’re grateful to be trusted with a job like this by AdventHealth.

Installing New Generators and Power Systems at AdventHealth’s East Orlando Campus

LEBS Electric recently completed a project at AdventHealth’s East Orlando campus including the installation of three new 2MW generators with provisions for a future fourth plus a new building housing the Emergency Distribution Equipment (EDP) and all associated power systems. Our team also delivered a completely new network control system for the facility’s 27 existing ATS units, strengthening reliability across the entire campus.

In the photos, you’ll see the impressive 450-ton Sims crane setting two new 2MW Ring Power generators along with two fuel day tanks. The Sims Rigging team skillfully received the generators and tanks and pulled them into place once the crane got them partially into the building. The entire operation was completed in less than six hours, all while the hospital maintained full operational capacity.

We’re grateful for the collaboration with Brasfield & Gorrie (General Contractor) and TLC Engineering (Engineer). Together, we’re building the resilient, dependable power systems that keep healthcare facilities ready when it matters most.